To Run a Sequence

A sequence is run one event at a time. Events can be skipped over by selecting a different event in the sequence as the next event.

  1. Click Navigation Menu > Live Assist > Sequencer > Run.


  2. Use the Up, Down, and Next buttons to run through the sequence.


    # Function
    1 The currently loaded sequence. This uses the mnemonic name and color.
    2 Multiple Sequencers can be linked together. This only affects the Next button and allows clicking Next on any of the linked Sequencers to advance all the linked Sequencers. There is only one linked group.
    3 The Reload, Clear, and Load buttons allow you to populate or clear the Sequencer.
    • Load — load a different sequence into the Sequencer.
    • Clear — unload the current sequence from the Sequencer.
    • Reload — reload or update the current sequence in the Sequencer.
    4 The red highlight shows the last run (current) sequence event.
    5 The green highlight shows the next event to be run. Click on a different event, or use the Up or Down buttons to select a different event to be run next.
    6 The Up and Down buttons move the green (run next) highlight up and down in the sequence.
    7 The Next button runs the event that is currently highlighted in green.